Consents and PIMs

1. Before you begin

Building consents are issued by the Council to verify that proposed work meets the New Zealand Building Code 1992, the Building Act 2004 and associated regulations. Building work cannot begin until the building consent (and Resource Consent if required) is issued.

Depending on your project, you may also need to consider other legislation such as the Natural and Built Environment Act 2023. Visit Property Information to see information on Land Information Memorandums, Natural Hazards, Resource Consents and Healthy Housing.

2. The Building Act

Building work in New Zealand is controlled by the Building Act 2004. This legislation is designed to ensure that buildings in New Zealand are built right the first time and that appropriately skilled people design, build and inspect building work.

To achieve this, the Act requires anyone proposing to do building work to firstly obtain a building consent (BC) from a building consent authority (BCA). A BCA is the part of Council that receives, grants and issues building consents, undertakes inspections and issues code compliance certificates.

The Building Act is administered by the Ministry of Business, Innovation and Employment (MBIE).

When is a building consent required?

If you’re planning any construction, demolition or alteration work, you’ll need building consent before work can begin. Building consent is also often needed for tents or marquees, pools, fireplaces, driveways and solar panels. There are some exemptions. If in doubt, talk to us or refer to MBIE guidance on work requiring consents.

Find more information on Building Consent FAQ page.

3. Apply for an amendment to a building consent & information relating to alterations to an existing building

If you wish to change some aspect of your building project after your consent has been approved you will need to apply for an amendment to the Building Consent before the work is carried out.

The process for obtaining an amendment is same as obtaining the original consent

It is very important that at the time of inspection the Building Consent documents accurately reflect what has been built.

Minor variations that don’t differ significantly from the plans and specifications can be approved on site at the time of inspection with the required minor variation form.

Applications for alterations to an existing building

In accordance with section 112 of the Building Act 2004, building consents can only be granted for alterations to existing buildings where the building consent authority is satisfied that the building will:

  • comply as nearly as is reasonably practicable with the Building Code provisions for means of escape from fire and access and facilities for people with disabilities (if required)
  • continue to comply with the other provisions of the Building Code to at least the same extent as before the alteration.

The Act clarifies that if part of a building is altered, the upgrade provisions are triggered for the whole building.

A territorial authority may, by written notice, grant an application to allow alterations to take place without the building complying with the relevant provisions of the Building Code. A territorial authority can only grant such an application if it is satisfied that:

  • if the building were to comply with the relevant provisions of the Building Code, the alteration would not take place
  • the alterations will result in improvements to the means of escape from fire or access and facilities for people with disabilities
  • the improvements outweigh any detriment likely to arise as a result of the other non-compliance with the Code.

Alterations to earthquake-prone buildings are now under section 133AT of the Building Act.

More information about the requirements for alterations to existing buildings can be found on the MBIE website

4. Fireplaces

If you’re planning to install a fireplace in your home you’ll need building consent. If your property is less than two hectares in lot size, you’ll need to choose a wood burner from a list approved by the Ministry for the Environment. Second hand fires will only be approved if they have been certified by the manufacturer. 

5. Building work that does not require a building consent

Only building work listed under Schedule 1 of the Building Act 2004 may be done without first obtaining a Building Consent, but the building work must still comply with the Building Code. Further information can be found in the exemption guide that the Ministry of Business, Innovation and Employment have developed.

Waitaki District Council allows an exemption for some pole sheds. Please see Application for Exemption Form - Pole Shed only(PDF, 273KB) to see if you meet the criteria. Please contact us for information and advice about exemptions and the building consent process.

6. Compliance Schedules

If your building work involves installing or altering specified systems we require the proposed installation standards, maintenance and reporting procedures to be included in your application. Please refer to the information on Commercial buildings and Compliance Schedules and Warrant Of Fitness

7. Restricted building work

Building and design work relating to a building’s structure, foundations, fire safety or moisture protection is classified as ‘restricted building work’. Restricted building work currently only relates to residential buildings, and can only be carried out by a Licensed Building Practitioner (LBP).

8. Licensed Building Practitioners (LBPs)

Licensed Building Practitioners (LBPs) are designers, carpenters, roofers, external plasterers, bricklayers and block layers and those who lay foundations, who are licensed under the Government's LBP scheme.

No restricted building works can start until Council has been notified of the names and licence numbers for the trade LBPs who will be doing the work.

Note: Registered architects and chartered professional engineers are automatically treated as Design LBPs. Licensed or certified plumbers are automatically treated as LBPs so that they are able to carry out and supervise fitting and sealing or flashing of pipe work through exterior walls and certain roofing and cladding work, in the ordinary course of their work.

The Public Register for current Licensed Building Practitioners can be found here.

Owner Builder Exemption 

The Owner-Builder Exemption ensures the Kiwi tradition of DIY building work can continue.  If you're a homeowner who qualifies for the exemption, you will not need to be or use a licensed building practitioner (LBP) for any restricted building work on your home. However, you will still need to apply for a building consent.

More information about LBP's can be found on the Ministry of Business, Innovation & Employment website.

More information about owner-builder exemptions can also be found on the MBIE website

Owner-builder exemptions forms are available on our application forms and guides page.

9. LBP Memorandums

Building consent applications for restricted building work must include a Memorandum (Certificate of Design Work) from the LBP.

At the end of the project, each LBP is required to provide a Memorandum (Record of Building Work), which details the work the LBP carried out.

Failure to provide all the required Memorandums could result in the Council being unable to issue the final Code of Compliance Certificate for the project.

Memorandum from Licensed Building Practitioner: Certificate of Design Work

Memorandum from Licensed Building Practitioner: Record of Building Work

 

10. Producer Statements 

A producer statement is a professional opinion based on sound judgment and specialist expertise. It is not a product warranty or guarantee of compliance. 

While producer statements are well-established and widely used, they have no particular status under the Building Act 2004. They are used as one source of information which the council may rely upon to determine whether there are reasonable grounds to conclude that the work complies with the Building Code.

In considering whether to accept a producer statement, a council will normally assess the credentials of the author to ensure that person has the appropriate experience and competence in their particular field of expertise and make their own inspections of the building work. For more information, check out Producer statements.

11. Property Information Memorandum (PIM)

A PIM is a memorandum issued under section 34 of the Building Act 2004 which provides information relevant to a proposed building project, and can include things like the location of services, likelihood of flooding, subsidence, and ground stability.

It’s also a way to find out about any other requirements you might need for your project, such as resource consents, vehicle crossings or other issues that may affect the design and/or construction of the proposed structure.

A PIM is optional, but we recommend you get one if your project is large or complex.

Although you can apply for a PIM at the same time as a building consent, it's better to do so beforehand, so you know all the matters that may affect your project before submitting your building consent application. PIM applications follow a similar process to a building consent application.

A PIM does not give you any form of approval under the WDC District Plan and is not an authorisation to commence work. You must wait until your building consent (and resource consent, if required) has been granted and issued before commencing work.

Application

The best time to apply for a PIM is before starting preliminary design work, so that we can give you accurate information about the consents and approvals you may need.

This application must be on Form 2 and include generic information as well as the following: 

  • details of the location of building work
  • description of building work
  • details of any change of use (if applicable) 
  • estimated value of building work
  • previous consents issued for the project (if applicable)  
  • subdivision details.

The Building Act 2004 requires this form to be accompanied by:

  • any information council reasonably requires in relation to authorisations or requirements in respect of:
    • the intended use of the proposed building
    • the location and external dimensions of the proposed building
    • provisions to be made for vehicle access in buildings over or adjacent to any road or public place, and for disposing of stormwater and wastewater
    • precautions to be taken if building work is carried out over any existing drains or sewers or in close proximity to wells or water mains
  • any other information council requires in respect of proposed connections to public utilities from the proposed building work.

You can apply for a PIM via the Objective Build portal, via email to building@waitaki.govt.nz or in person:

  • Main office - 20 Thames Street, Oamaru
  • Waihemo Service Centre – 54 Tiverton Street, Palmerston

Processing

Council can request further information from the applicant within 10 working days of receiving the application and suspend the application until it receives the information.

Requests can be made for further information in relation to authorisations or requirements (intended use, location and dimensions, vehicle access and roading, stormwater and wastewater disposal, proximity to drains etc.) and about proposed connections to public utilities.

Council must advise the New Zealand Historic Places Trust within five days of receiving a PIM application that affects a registered historic place, historic area, waahi tapu or waahi tapu area.

Issuing

The PIM must be issued within 20 working days from the date of receiving the application, or within 10 days after any further information has been received.

The PIM must include all the information likely to be relevant to the proposed building work, including:

  • information identifying each special feature of the land concerned (if any).
  • information that, in terms of any other Act, has been notified to the territorial authority by a statutory authority.
  • details of existing stormwater or wastewater utility systems on, or adjacent to, the site of the proposed building work or that relate to the proposed building work.
  • details of any authorisation (including requirements to be met and conditions) in respect of the proposed building work that the territorial authority, on its own behalf and on behalf of any network utility operator, is authorised to refuse or require under any other Act.
  • either confirmation that the building work may be carried out subject to the requirements of a building consent and subject also to all other necessary authorisations being obtained, or notification that building work may not be carried out because any necessary authorisation has been refused, despite the issue of any building consent.
  • if the PIM relates to the construction of a building on land composed of two or more allotments, the statement referred to in section 75(2) of the Building Act.

Plus, where applicable:

  • information regarding the heritage status of the building.
  • a statement, if the building is of historic nature, that the New Zealand Historic Places Trust will be (or has been) notified.
  • if the territorial authority considers that the owner of the building is likely to be required to make provision for an evacuation scheme under section 21A of the Fire Service Act 1975, a statement to that effect.
  • attach a notice under section 36 advising that a development contribution under the Local Government Act 2002 will need to be paid before a code compliance certificate can be issued.
  • a certificate under section 37 stating that building work may not proceed until a resource consent has been obtained or may only proceed to the extent stated in the certificate.

A certificate (Form 4) must be attached to the issued PIM.

More information about PIMs can be found on the MBIE website.

Fees

Please see our current fees and charges for PIMs under fees for property information services.

12. Public access while building or altering a public building

If the public uses all or part of your building, and you want them to access it before your building work has been signed off as complete, you can apply through the BUILD portal or using this form - Application for Certificate for Public Use. Your application will need to show that all or part of the building (whatever you are applying for) can be used safely by members of the public. i.e.. Any specified systems must remain operational.